# Anderson Columbia Co., INC.: TxDOT rehabilitation of existing road contract 8% complete, SH 16, Jim Hogg County ($5,580,787, 4 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Anderson Columbia Co., INC. |
| Subcontractors | Rc Contract Services LLC (0%); K. L. Durham Construction, L.L.C. (0%); J. H. Oden Contracting Company (0%); Highway Barricades And Services, LLC (7.58%) |
| Progress | 8.18% complete, 0.59% of time used |
| Amount | $5,580,787 revised (original $5,520,580) |
| Change orders | $23,861 |
| Paid to date | $453,431 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 16, TILLEY ST. to DRAPER ST., Jim Hogg County, Pharr District |
| Let / began | 2025-06-04 |
| Latest estimate | 2026-10-02 |
| Contract number | 6253011 |

## Why this score
- Contract over $1M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.