# Anderson Columbia Co., INC.: TxDOT new location freeway contract 27% complete, US 77, Kleberg County ($178,365,453, 15 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Anderson Columbia Co., INC. |
| Subcontractors | Rio Grande Rebar Rodbusters, LLC (0%); Texas Steel Industrial Placing, LLC (0.12%); Foremost Paving, INC. (21.13%); Roadway Specialties, INC. (0.25%); M & D Foundation Drilling Industries, INC. (0.68%); Highway Barricades And Services, LLC (0.28%); Primate Construction, LP (0.01%); Jhabores Construction Co., INC. (1.01%); Texas Environmental Management - San Antonio, INC. (0.87%); Performance Equipment Service (0.11%); Southwest Road & Safety Contractors, LTD. (0.22%); Traf-Tex, INC. (2.43%); Structural Integrity Group LLC (0.5%); Scott Derr Painting Co, LLC (0.26%); Izaguirre Construction LLC (1.84%) |
| Progress | 27.43% complete, 13.49% of time used |
| Amount | $178,365,453 revised (original $178,365,453) |
| Paid to date | $48,919,987 |
| Work | New Location Freeway |
| Location | US 77, 1.5 MI N. OF SH 285 INTERSECTION to KENEDY/KLEBERG COUNTY LINE, Kleberg County, Corpus Christi District |
| Let / began | 2025-07-01 / 2026-01-05 |
| Latest estimate | 2026-10-02 |
| Contract number | 7253001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.