# Anderson Columbia Co., INC.: TxDOT widen non-freeway contract 95% complete, SH 359, Webb County ($49,895,267, 11 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Anderson Columbia Co., INC. |
| Subcontractors | K. L. Durham Construction, L.L.C. (1.1%); Acee Construction LLC. (15.18%); Eggemeyer Land Clearing, LLC (0.28%); Highway Barricades And Services, LLC (0.67%); Professional Traffic Control LLC (0.03%); Southwest Road & Safety Contractors, LTD. (0%); Texas Icon Construction, LLC (6.43%); Traf-Tex, INC. (1.09%); Ramiro Ramirez Construction, INC. (0.07%); 4e Tree Worx LLC (0.01%); Hart Services LLC (0.01%) |
| Progress | 94.73% complete, 98.26% of time used |
| Amount | $49,895,267 revised (original $47,686,786) |
| Change orders | $2,208,482 |
| Paid to date | $47,264,782 |
| Work | Widen Non-Freeway |
| Location | SH 359, 4.06 MILES E OF SL 20 to 8.935 MILES E OF SL 20, Webb County, Laredo District |
| Let / began | 2023-08-02 / 2024-01-29 |
| Latest estimate | 2026-10-05 |
| Contract number | 8233057 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.