# Aranda Brothers Construction Co., INC.: TxDOT bridge replacement contract 95% complete, CS, Harris County ($4,551,587, 3 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Aranda Brothers Construction Co., INC. |
| Subcontractors | Bell Bottom Foundation Co. (3.31%); Traffic Signs & Lines, LLC (0.16%); Traf-Tex, INC. (1.35%) |
| Progress | 94.97% complete, 100.37% of time used |
| Amount | $4,551,587 revised (original $4,303,858) |
| Change orders | $196,082 |
| Paid to date | $4,273,623 |
| Work | Bridge Replacement |
| Location | CS, DIAMONDHEAD BLVD AT GUM GULLY to ., Harris County, Houston District |
| Let / began | 2023-02-01 / 2023-06-08 |
| Latest estimate | 2026-10-12 |
| Contract number | 2233023 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.