# Austin Bridge & Road Services, LP: TxDOT interchange (new or reconstructed) contract 77% complete, IH 30, Hunt County ($134,220,720, 27 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Austin Bridge & Road Services, LP |
| Subcontractors | Highway Intelligent Traffic Solutions, LLC (2.05%); Withers Construction, LLC (0.07%); Act Saw Cutting & Removal (0.1%); Antigo Construction, INC. (0.09%); Hammett Excavation, INC. (9.38%); Peachtree Construction, LTD. (1.25%); Wylie Drilling & Drainage, INC. (0.64%); Farr Foundation, INC. (1.46%); King George Traffic Solutions LLC (0.96%); Slaton Bros, INC. (0.4%); (Inactive)royal Rebar (3.22%); Texop Construction (0.01%); Scott Derr Painting Co, LLC (0.02%); J. H. Oden Contracting Company (0.26%); Southern Cross Contractors, LLC (0%); USA Swppp Inspections, INC. (0.48%); Hart Services LLC (0.09%); Monarrez Trucking LLC. (0.04%); A-Core Concrete Cutting Of Texas, INC. (0.02%); Gibson & Associates, INC. (0.01%); Fga Construction LLC (0%); Striping Technology, L.P. (0.99%); Stoic Civil Construction, INC. (0.05%); (Inactive)site Barricades (0.08%); Texas Traffic And Barricade, LLC (0.07%); Fortson Contracting, INC. (0.26%); Traffic Tech Solutions, LLC (0%) |
| Progress | 76.98% complete, 82.51% of time used |
| Amount | $134,220,720 revised (original $128,075,439) |
| Change orders | $5,103,713 |
| Paid to date | $102,515,966 |
| Work | Interchange (New Or Reconstructed) |
| Location | IH 30, IH 30 FROM 1 MI W OF FM 1903 TO 1.2 MI E OF FM 1903, Hunt County, Paris District |
| Let / began | 2022-10-06 / 2023-03-15 |
| Latest estimate | 2026-10-05 |
| Contract number | 10223002 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.