# Austin Bridge & Road Services, LP: TxDOT rehabilitation of existing road contract 100%+ complete, SH 121, Tarrant County ($29,002,677, 17 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Austin Bridge & Road Services, LP |
| Subcontractors | Massey Contractors, LLC (0.1%); West Texas Rock Resources, LLC (0.03%); Traffic Highway Maintenance, LLC (0.93%); Act Saw Cutting & Removal (1.1%); Area Wide Protective, INC. (0.3%); C. Green Scaping, L.P. (0.26%); Fortson Contracting, INC. (1.82%); Lollar Construction Group LLC (3.25%); Mica Corporation (1.42%); Mobile Enterprises, INC. (3.11%); Paniolo Construction Services, LLC (9.16%); S & S Bridge Painting, INC. (1.5%); G J Seeding, LLC (0.09%); Texas Traffic And Barricade, LLC (0.11%); Bcac Underground LLC (0.05%); Gibson & Associates, INC. (0.05%); Ace's Welding & Fabrication LLC (1%) |
| Progress | 103.94% complete, 100% of time used |
| Amount | $29,002,677 revised (original $25,141,983) |
| Change orders | $3,369,194 |
| Paid to date | $29,633,261 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 121, GILVIN ST to MIDWAY, Tarrant County, Fort Worth District |
| Let / began | 2022-12-02 / 2023-06-05 |
| Latest estimate | 2026-10-05 |
| Contract number | 12223204 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.