# Austin Bridge & Road Services, LP: TxDOT widen freeway contract 98% complete, IH 35, Cooke County ($213,440,165, 44 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Austin Bridge & Road Services, LP |
| Subcontractors | Zachry Construction Corporation (0%); Hermanos Steel, LLC (0.04%); Venus Construction Company (0.78%); Ray's Threading And Fab Shop (0.62%); Highway Pavement Specialties, INC. (0.21%); Toro Bravo Construction, LLC (5.94%); Potere Construction LLC (0.67%); Mcryan Hauling, INC. (0%); Tim Anthony Services, LLC (0%); Trp Construction Group, LLC (0.61%); Blue Rock Drilling, LLC (0.05%); Southeast Grinding And Grooving LLC (0.02%); Texas Shafts, INC. (0.67%); Traffic Tech Solutions, LLC (0.03%); Penhall Company (0.01%); Pathcom LLC (0.06%); Ddm Materials, INC. (0.01%); Allied Drilling Company (0.01%); Presley Land Management LLC (0%); Slaton Bros, INC. (0.23%); Rayray Underground LLC (0.12%); Magnum Manhole & Underground Company (0.01%); Hart Services LLC (0.01%); Groundworks Texas Poly, LLC (0%); Antigo Construction, INC. (0.24%); Oscar Orduno, INC. (1.59%); Wims Environmental Construction, LTD. (1.26%); Monarrez Trucking LLC. (0%); Dale Brown, INC. (0.14%); Time Striping, INC. (0.05%); A R Daniel Construction Services, Incorporated (0.17%); Straight Line Sawing & Sealing, INC. (0%); Withers Construction, LLC (0%); Freight Operation Services, LLC, DBA Fos Brokerage Services (0%); Khonsu Enterprise LLC (0.37%); Skaggs Road Boring, INC. (0.15%); Double Ee Contractors, LLC (0.02%); H & H Concrete On Demand INC (0.55%); Southern Cross Contractors, LLC (0.06%); 1 Priority Environmental Services, LLC (0.11%); Fortson Contracting, INC. (0.58%); (Inactive)highway Intelligent Traffic Solutions, INC. (4.39%); Scott Derr Painting Co, LLC (0.07%); W.O.E. Construction, INC. (2.22%) |
| Progress | 97.54% complete, 98.28% of time used |
| Amount | $213,440,165 revised (original $209,999,113) |
| Change orders | $2,392,000 |
| Paid to date | $207,157,250 |
| Work | Widen Freeway |
| Location | IH 35, 1.4 MI SOUTH OF SPRING CREEK ROAD to 0.2 MI SOUTH OF US 82, Cooke County, Wichita Falls District |
| Let / began | 2021-02-05 / 2021-06-21 |
| Latest estimate | 2026-10-01 |
| Contract number | 2213201 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.