# Austin Bridge & Road Services, LP: TxDOT widen freeway contract 53% complete, IH 35, Cooke County ($487,165,907, 32 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Austin Bridge & Road Services, LP |
| Subcontractors | Zachry Construction Corporation (0%); Comal Aggregate LLC (0.1%); Texas Environmental Management - San Antonio, INC. (0.12%); Toro Bravo Construction, LLC (4.29%); American Rehab And Inspection, INC. (0.01%); (Inactive)royal Rebar (0.04%); C&C Tx Concrete Pumping, LLC (0.01%); USA Swppp Inspections, INC. (0.17%); Traffic Highway Maintenance, LLC (0.57%); A&A Aggregates, INC. (0%); Venus Construction Company (2.86%); Slaton Bros, INC. (0.06%); Skaggs Road Boring, INC. (0.01%); Primate Construction, LP (0.03%); Scott Derr Painting Co, LLC (0.03%); Stoic Civil Construction, INC. (0.05%); Rambo Contracting, INC. (0.23%); Surface Preparation Technologies, LLC (0.01%); Mulholland Energy Services, LLC (0.01%); Antigo Construction, INC. (0.14%); Red Top Trucking LLC (1.87%); Jb Pinnacle Group, LLC (1.03%); Farr Foundation, INC. (0.65%); Ats Drilling, INC. (1.68%); Highway Intelligent Traffic Solutions, LLC (3.53%); Southwest Road & Safety Contractors, LTD. (0.18%); Oscar Orduno, INC. (1.69%); T-Bar Fence, INC. (0.06%); Act Saw Cutting & Removal (0.2%); Blue Rock Drilling, LLC (0.08%); Buyers Barricades, INC. (0.06%); A R Daniel Construction Services, Incorporated (0.09%) |
| Progress | 52.53% complete, 36.15% of time used |
| Amount | $487,165,907 revised (original $482,134,095) |
| Change orders | $1,750,920 |
| Paid to date | $254,187,981 |
| Work | Widen Freeway |
| Location | IH 35, ON IH 35 AT THE RED RIVER BRIDGE to ., Cooke County, Wichita Falls District |
| Let / began | 2024-04-05 / 2024-10-07 |
| Latest estimate | 2026-10-01 |
| Contract number | 4243202 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.