# Austin Bridge & Road Services, LP: TxDOT interchange (new or reconstructed) contract 52% complete, IH 635, Dallas County ($548,189,139, 32 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Austin Bridge & Road Services, LP |
| Subcontractors | Durable Specialties, INC. (0%); Jb Pinnacle Group, LLC (0.77%); Good Earth Corporation (0.04%); Act Saw Cutting & Removal (0.19%); Q. Roberts Trucking Incorporated (0.17%); Synergy Signs & Services LLC (0.1%); Surface Preparation Technologies, LLC (0.01%); Texas Shafts, INC. (3.41%); Texas Environmental Management - San Antonio, INC. (0.61%); Houston Sawing & Drilling (0.04%); USA Swppp Inspections, INC. (0.13%); Royal Rebar INC (3.34%); Tor Texas, LLC (0.01%); North Texas Contracting, INC. (6.23%); Choctaw Erectors, INC. (0.4%); Fortson Contracting, INC. (0.23%); Antigo Construction, INC. (0.07%); (Inactive)royal Rebar (0%); Texop Construction (0%); Stripe-A-Zone, LLC (0%); Traffic Highway Maintenance, LLC (0.35%); Dywidag-Systems International_usa,INC. (0.03%); J.H. Painting Company (0.17%); Lindamood, INC. (0.86%); Mica Corporation (2.88%); Oscar Orduno, INC. (3.04%); Slaton Bros, INC. (2.24%); Keller North America, INC. (0.15%); Hdw Construction & Drilling, LLC. (0%); A R Daniel Construction Services, Incorporated (0%); Superior Traffic Control, LLC (0.1%); Breda Company, INC. (0%) |
| Progress | 51.72% complete, 38.58% of time used |
| Amount | $548,189,139 revised (original $539,664,225) |
| Change orders | $2,242,614 |
| Paid to date | $280,256,920 |
| Work | Interchange (New Or Reconstructed) |
| Location | IH 635, AT US 80 INTERCHANGE to ., Dallas County, Dallas District |
| Let / began | 2024-07-10 / 2025-02-24 |
| Latest estimate | 2026-10-02 |
| Contract number | 7243201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.