# Austin Bridge & Road Services, LP: TxDOT maintenance contract 65% complete, IH0030, Tarrant County ($7,220,025)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Austin Bridge & Road Services, LP |
| Progress | 65.32% complete, 48.63% of time used |
| Amount | $7,220,025 revised (original $3,130,822) |
| Change orders | $4,090,308 |
| Paid to date | $4,716,726 |
| Work | Maintenance |
| Location | IH0030, VARIOUS LOCATIONS IN to SOUTH TARRANT COUNTY, Tarrant County, Fort Worth District |
| Let / began | 2025-07-02 / 2025-10-06 |
| Latest estimate | 2026-09-29 |
| Contract number | 7254215 |

## Why this score
- Contract over $1M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.