# *austin Traffic Signal Construction Co., INC.: TxDOT traffic signal contract 95% complete, FM 3024, Live Oak County ($1,185,800, 2 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | *austin Traffic Signal Construction Co., INC. |
| Subcontractors | G & E Escobedo Construction, INC. (3.49%); Highway Barricades And Services, LLC (12.44%) |
| Progress | 95.08% complete, 88.82% of time used |
| Amount | $1,185,800 revised (original $1,021,498) |
| Change orders | $164,302 |
| Paid to date | $1,127,416 |
| Work | Traffic Signal |
| Location | FM 3024, 1000 FT N OF FM 534 to 1000 S OF FM 534, Live Oak County, Corpus Christi District |
| Let / began | 2025-06-04 / 2025-09-22 |
| Latest estimate | 2026-10-02 |
| Contract number | 6253039 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.