# *austin Traffic Signal Construction Co., INC.: TxDOT traffic signal contract 71% complete, SH 495, Hidalgo County ($3,525,673, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | *austin Traffic Signal Construction Co., INC. |
| Subcontractors | Texas Highway Systems, INC. (4.13%); G & E Escobedo Construction, INC. (2.28%); Rio Grande Constructors And Construction Management LLC (3.16%); Pavement Markings INC. (9.31%) |
| Progress | 70.88% complete, 54.93% of time used |
| Amount | $3,525,673 revised (original $3,504,673) |
| Paid to date | $2,484,096 |
| Work | Traffic Signal |
| Location | SH 495, 0.1 MI. W. OF CESAR CHAVEZ RD. to 0.1 MI. E. OF CESAR CHAVEZ RD., Hidalgo County, Pharr District |
| Let / began | 2025-08-07 / 2026-01-15 |
| Latest estimate | 2026-10-02 |
| Contract number | 8253008 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.