# Baker & Company Construction, LLC: TxDOT rehabilitation of existing road contract 100%+ complete, FM 1651, Van Zandt County ($11,020,766, 9 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Baker & Company Construction, LLC |
| Subcontractors | Texana Land & Asphalt, INC. (43.15%); Southwest Environment Services LLC (0.73%); Jm Yanez Construction, INC. (10.31%); Flex Supply, LLC (0.17%); Dustrol, INC. (0.2%); Professional Traffic Control LLC (0.13%); Catocon, INC. (1.7%); Striping Technology, L.P. (1.27%); Need Grass Now LLC (2.43%) |
| Progress | 105.79% complete, 102.34% of time used |
| Amount | $11,020,766 revised (original $10,542,339) |
| Change orders | $195,606 |
| Paid to date | $11,359,517 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 1651, SH 198 E. to SH 19, Van Zandt County, Tyler District |
| Let / began | 2024-05-03 / 2024-08-19 |
| Latest estimate | 2026-10-02 |
| Contract number | 5243207 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.