# Baker & Company Construction, LLC: TxDOT hazard elimination & safety contract 23% complete, SH 34, Hunt County ($4,598,236, 8 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Baker & Company Construction, LLC |
| Subcontractors | Flex Supply, LLC (0.19%); Catocon, INC. (1.57%); Need Grass Now LLC (3.34%); Texana Land & Asphalt, INC. (35.43%); Dustrol, INC. (0.59%); Jm Yanez Construction, INC. (10.09%); Striping Technology, L.P. (0.99%); Southwest Environment Services LLC (0.4%) |
| Progress | 23.09% complete, 11.81% of time used |
| Amount | $4,598,236 revised (original $4,125,934) |
| Change orders | $256,610 |
| Paid to date | $1,011,932 |
| Work | Hazard Elimination & Safety |
| Location | SH 34, SH 34 FROM TRADERS ROAD TO FM 1570, Hunt County, Paris District |
| Let / began | 2025-05-02 / 2025-07-08 |
| Latest estimate | 2026-10-05 |
| Contract number | 5253220 |

## Why this score
- Contract over $1M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.