# Balfour Beatty Infrastructure, INC.: TxDOT widen freeway contract 22% complete, IH 30, Dallas County ($897,823,162, 28 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Balfour Beatty Infrastructure, INC. |
| Subcontractors | Durable Specialties, INC. (0%); Circle H Boring, LLC (0%); Act Saw Cutting & Removal (0.03%); Southeast Grinding And Grooving LLC (0.02%); USA Swppp Inspections, INC. (0.08%); J.H. Painting Company (0.06%); Lindamood, INC. (0.73%); Breda Company, INC. (0%); Asfi Construction, L.L.C (0.3%); Quality Staffing Now, INC. (0.06%); Royal Rebar INC (3.56%); Panther Creek Transportation, INC. (0.27%); A R Daniel Construction Services, Incorporated (0.39%); Dustrol, INC. (0.07%); Farr Foundation, INC. (0.71%); Southern Cross Contractors, LLC (0.01%); Choctaw Erectors, INC. (4.74%); Cowboy Trucking (0.26%); Mica Corporation (5.12%); Harper Brothers Construction LLC (4.11%); Iron Wolf Construction Company LLC (0.03%); Hernandez Underground Contracting LLC (0%); Stripe-A-Zone, LLC (0%); Railworks Track Systems LLC (3.68%); Austin Bridge & Road Services, LP (1.69%); National Dewatering Systems (0%); Traffic Highway Maintenance, LLC (0.11%); A. H. Beck Foundation Co., INC. (5.14%) |
| Progress | 21.85% complete, 14.38% of time used |
| Amount | $897,823,162 revised (original $888,696,937) |
| Change orders | $3,505,025 |
| Paid to date | $194,967,458 |
| Work | Widen Freeway |
| Location | IH 30, IH 35E to IH 45, Dallas County, Dallas District |
| Let / began | 2025-02-07 / 2026-01-05 |
| Latest estimate | 2026-10-02 |
| Contract number | 2253201 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.