# Big Creek Construction, LTD.: TxDOT rehabilitation of existing road contract 30% complete, US, Lampasas County ($57,196,849, 10 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Big Creek Construction, LTD. |
| Subcontractors | D. I. J. Construction, INC. (1.23%); Professional Traffic Control LLC (0.08%); Bear Creek Construction, LLC (9.82%); Buyers Barricades Austin, LLC (0.2%); F & W Electrical Contractors, INC. (0.63%); Southwest Road & Safety Contractors, LTD. (0.18%); Dallas Lite And Barricade, INC. (0.12%); J. H. Oden Contracting Company (0.58%); Vortex Lining Systems, LLC (1.17%); Landtamers LLC (0.33%) |
| Progress | 29.78% complete, 22.22% of time used |
| Amount | $57,196,849 revised (original $54,760,409) |
| Paid to date | $16,308,511 |
| Work | Rehabilitation Of Existing Road |
| Location | US, 8.53 MI. NORTHWEST OF LAMPASAS to US 281, Lampasas County, Brownwood District |
| Let / began | 2025-10-09 / 2026-02-02 |
| Latest estimate | 2026-09-30 |
| Contract number | 10253201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.