# Big Creek Construction, LTD.: TxDOT widen non-freeway contract 25% complete, SH 19, Van Zandt County ($11,228,661, 10 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Big Creek Construction, LTD. |
| Subcontractors | Diamond Elite Barricades, LLC (0.2%); Cold Creek Construction, LTD (3.19%); Dustin Allen, INC. (1.79%); Marcoms Construction LLC (0.7%); Mobile Enterprises, INC. (0.1%); Surface Preparation Technologies, LLC (0.14%); Striping Technology, L.P. (1.03%); J. H. Oden Contracting Company (2.59%); Flex Supply, LLC (0.06%); Jm Yanez Construction, INC. (11.8%) |
| Progress | 24.67% complete, 54.55% of time used |
| Amount | $11,228,661 revised (original $11,187,838) |
| Paid to date | $2,759,660 |
| Work | Widen Non-Freeway |
| Location | SH 19, US 80, S to IH 20, IN CANTON, Van Zandt County, Tyler District |
| Let / began | 2025-11-06 / 2026-01-13 |
| Latest estimate | 2026-10-02 |
| Contract number | 11253227 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.