# Big Creek Construction, LTD.: TxDOT overlay contract 100%+ complete, FM 279, Van Zandt County ($7,888,097, 11 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Big Creek Construction, LTD. |
| Subcontractors | Bahena Construction Co., INC. (2.14%); Cold Creek Construction, LTD (6.87%); Diamond Elite Barricades, LLC (0.15%); Dustin Allen, INC. (0.51%); (Inactive)hogan Murray, INC. (1.89%); J. H. Oden Contracting Company (5.23%); Mobile Enterprises, INC. (0.41%); Stripe-A-Zone, LLC (2.22%); West Texas Rock Resources, LLC (0.24%); Next Construction Solutions LLC (0.03%); Flex Supply, LLC (0.06%) |
| Progress | 110.38% complete, 102.99% of time used |
| Amount | $7,888,097 revised (original $7,787,125) |
| Change orders | $67,970 |
| Paid to date | $8,670,607 |
| Work | Overlay |
| Location | FM 279, .24 MI E OF FM 314 to SMITH C/L, Van Zandt County, Tyler District |
| Let / began | 2025-01-07 / 2025-04-10 |
| Latest estimate | 2026-10-02 |
| Contract number | 1253008 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.