# Big Creek Construction, LTD.: TxDOT interchange (new or reconstructed) contract 92% complete, SH 31, Mclennan County ($29,785,840, 16 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Big Creek Construction, LTD. |
| Subcontractors | Bear Creek Construction, LLC (4.4%); Toro Bravo Construction, LLC (0.21%); Next Construction Solutions LLC (0%); Aaron Concrete Contractors, LLC (0.31%); Wims Environmental Construction, LTD. (1.19%); Cen Tex Hydroseed, INC. (0.55%); Cen-Tree Solutions LLC (0.19%); Wolfe Construction Group, Incorporated (0.17%); Trp Construction Group, LLC (1.01%); Dallas Lite And Barricade, INC. (0.14%); *austin Traffic Signal Construction Co., INC. (0.29%); Murray Construction (0.33%); M & D Foundation Drilling Industries, INC. (1.83%); Primate Construction, LP (0.06%); Professional Traffic Control LLC (0.04%); Roadway Specialties, INC. (1.76%) |
| Progress | 91.54% complete, 88.78% of time used |
| Amount | $29,785,840 revised (original $29,287,263) |
| Change orders | $498,577 |
| Paid to date | $27,265,757 |
| Work | Interchange (New Or Reconstructed) |
| Location | SH 31, ON SH 31, FROM 0.5 MI S OF FM 2311 TO 0.5 MI N OF FM 2311 to ON FM 2311, FROM FM 308 TO SH 31, Mclennan County, Waco District |
| Let / began | 2024-05-02 / 2024-08-12 |
| Latest estimate | 2026-10-05 |
| Contract number | 5243003 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.