# Big Creek Construction, LTD.: TxDOT rehabilitation of existing road contract 81% complete, FM 50, Robertson County ($20,736,867, 8 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Big Creek Construction, LTD. |
| Subcontractors | Bayer Construction Electrical Contractors, INC. (0.14%); Cen-Tree Solutions LLC (0.16%); Professional Traffic Control LLC (0.03%); Stripe Lines, INC. (1.9%); Texas Environmental Management - San Antonio, INC. (3.38%); Willow City Sign & Rail, INC. (1.23%); Gk Construction, LLC (0.01%); M & D Foundation Drilling Industries, INC. (0%) |
| Progress | 81.14% complete, 61.77% of time used |
| Amount | $20,736,867 revised (original $20,558,088) |
| Change orders | $24,258 |
| Paid to date | $16,700,261 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 50, US 79 to BRAZOS COUNTY LINE, Robertson County, Bryan District |
| Let / began | 2025-05-02 / 2025-07-28 |
| Latest estimate | 2026-10-01 |
| Contract number | 5253239 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.