# Big Creek Construction, LTD.: TxDOT widen non-freeway contract 98% complete, US 175, Anderson County ($59,553,583, 15 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Big Creek Construction, LTD. |
| Subcontractors | 1 Priority Environmental Services, LLC (0.04%); A-Core Concrete Cutting Of Texas, INC. (0.04%); Ancortex, INC. (1.31%); J & M Contracting, Company (6.85%); Stripe-A-Zone, LLC (0.03%); Toro Bravo Construction, LLC (0.31%); Whm Construction, INC. (0.08%); A&J Rebar LLC (0.06%); Dustin Allen, INC. (0.19%); Next Construction Solutions LLC (0%); Flex Supply, LLC (0.13%); Southwest Environment Services LLC (0.18%); Striping Technology, L.P. (0.44%); J. H. Oden Contracting Company (3.07%); Scott Derr Painting Co, LLC (0.03%) |
| Progress | 97.95% complete, 104.15% of time used |
| Amount | $59,553,583 revised (original $55,487,305) |
| Change orders | $723,551 |
| Paid to date | $55,057,211 |
| Work | Widen Non-Freeway |
| Location | US 175, 0.4 MI SE OF SH 155, SE to CHEROKEE C/L AT NECHES RIVER, Anderson County, Tyler District |
| Let / began | 2022-06-30 / 2022-10-24 |
| Latest estimate | 2026-10-02 |
| Contract number | 6223602 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.