# Big Creek Construction, LTD.: TxDOT rehabilitation of existing road contract 96% complete, SH 34, Ellis County ($13,343,066, 9 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Big Creek Construction, LTD. |
| Subcontractors | West Texas Rumble Strip LLC (0.23%); Next Construction Solutions LLC (0.01%); J & M Contracting, Company (0%); Je Casey, LLC (0%); Dallas Lite And Barricade, INC. (0%); Professional Traffic Control LLC (0%); Synergy Signs & Services LLC (0%); Traffic Highway Maintenance, LLC (0%); USA Swppp Inspections, INC. (0%) |
| Progress | 96.29% complete, 95.65% of time used |
| Amount | $13,343,066 revised (original $12,687,858) |
| Change orders | $166,107 |
| Paid to date | $12,376,829 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 34, US 77 to BI 45-G, Ellis County, Dallas District |
| Let / began | 2024-06-06 / 2024-11-06 |
| Latest estimate | 2026-10-05 |
| Contract number | 6243213 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.