# Big Creek Construction, LTD.: TxDOT bridge replacement contract 66% complete, SH 30, Grimes County ($12,568,401, 14 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Big Creek Construction, LTD. |
| Subcontractors | Willow City Sign & Rail, INC. (1.14%); West Texas Rock Resources, LLC (0.04%); Lonestar Traffic Safety, LLC (0.1%); M & D Foundation Drilling Industries, INC. (4.26%); Toro Bravo Construction, LLC (0.82%); Wilko Industrial, L.L.C. (0.24%); (Inactive)mesa Rod Busters, INC. (0.11%); West Texas Rumble Strip LLC (0.04%); Cen Tex Hydroseed, INC. (0.99%); Eggemeyer Land Clearing, LLC (0.53%); Highway 1 LLC (0.64%); Houston Sawing & Drilling (0.13%); Trp Construction Group, LLC (0.64%); Emery Sapp & Son's INC. (0.08%) |
| Progress | 66.11% complete, 73.66% of time used |
| Amount | $12,568,401 revised (original $12,337,845) |
| Change orders | $154,822 |
| Paid to date | $8,259,418 |
| Work | Bridge Replacement |
| Location | SH 30, AT GIBBONS CREEK to ., Grimes County, Bryan District |
| Let / began | 2024-06-06 / 2024-11-11 |
| Latest estimate | 2026-10-02 |
| Contract number | 6243216 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.