# Big Creek Construction, LTD.: TxDOT hazard elimination & safety contract 93% complete, US 183, Mills County ($4,574,425, 3 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Big Creek Construction, LTD. |
| Subcontractors | Roadway Specialties, INC. (3.69%); Highway Traffic Control & Services, LLC (1.57%); D. I. J. Construction, INC. (8.56%) |
| Progress | 93.02% complete, 80.61% of time used |
| Amount | $4,574,425 revised (original $4,457,730) |
| Change orders | $6,600 |
| Paid to date | $4,152,543 |
| Work | Hazard Elimination & Safety |
| Location | US 183, 0.70 MI S. OF SH 16 to 0.11 MI N. OF CR 330, Mills County, Brownwood District |
| Let / began | 2025-06-05 / 2025-10-06 |
| Latest estimate | 2026-09-29 |
| Contract number | 6253214 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.