# Big Creek Construction, LTD.: TxDOT widen non-freeway contract 100%+ complete, FM 60, Burleson County ($35,354,638, 15 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Big Creek Construction, LTD. |
| Subcontractors | Toro Bravo Construction, LLC (0.27%); S & S Bridge Painting, INC. (0.05%); Primate Construction, LP (0.07%); M & D Foundation Drilling Industries, INC. (1.39%); Wims Environmental Construction, LTD. (2.3%); Willow City Sign & Rail, INC. (0.67%); Traffic Signs & Lines, LLC (0.18%); Citylynx, INC. (0.47%); Flasher Equipment Company (0.68%); Cen Tex Hydroseed, INC. (0.33%); Sarvicus LLC (0.66%); Gibson & Associates, INC. (0.28%); Aaron Concrete Contractors, LLC (0.76%); West Texas Rumble Strip LLC (0.05%); Cap River LLC (2.59%) |
| Progress | 101.85% complete, 98.17% of time used |
| Amount | $35,354,638 revised (original $34,287,618) |
| Change orders | $457,157 |
| Paid to date | $35,388,980 |
| Work | Widen Non-Freeway |
| Location | FM 60, SH 36 to 2.0 MILES EAST OF SH 36 NEAR CR 426, Burleson County, Bryan District |
| Let / began | 2021-07-02 / 2021-11-08 |
| Latest estimate | 2026-10-01 |
| Contract number | 7213202 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.