# Big Creek Construction, LTD.: TxDOT rehabilitation of existing road contract 99% complete, FM 937, Robertson County ($8,561,397, 9 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Big Creek Construction, LTD. |
| Subcontractors | (Inactive)fredonia Construction Services (0.01%); Professional Traffic Control LLC (0.15%); Dustin Allen, INC. (0.32%); Highway Traffic Control & Services, LLC (0.48%); Murray Construction (0.63%); Bayer Construction Electrical Contractors, INC. (1.47%); Cen Tex Hydroseed, INC. (3.39%); Cen-Tree Solutions LLC (0.82%); D. I. J. Construction, INC. (1.21%) |
| Progress | 98.68% complete, 97.04% of time used |
| Amount | $8,561,397 revised (original $9,087,363) |
| Change orders | $-577,743 |
| Paid to date | $8,397,327 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 937, LIMESTONE COUNTY LINE to SH 7, Robertson County, Bryan District |
| Let / began | 2023-08-03 / 2023-11-27 |
| Latest estimate | 2026-10-02 |
| Contract number | 8233212 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.