# Big Creek Construction, LTD.: TxDOT rehabilitation of existing road contract 21% complete, SH 159, Austin County ($12,747,743, 6 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Big Creek Construction, LTD. |
| Subcontractors | Stripe Lines, INC. (1.17%); Cen Tex Hydroseed, INC. (0.51%); Willow City Sign & Rail, INC. (1.37%); Cen-Tree Solutions LLC (0.15%); Third Coast Services LLC (0.39%); Dallas Lite And Barricade, INC. (0.56%) |
| Progress | 21.02% complete, 35.76% of time used |
| Amount | $12,747,743 revised (original $12,637,640) |
| Paid to date | $2,656,858 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 159, FAYETTE C/L to FM 109, Austin County, Yoakum District |
| Let / began | 2025-08-07 / 2026-05-05 |
| Latest estimate | 2026-10-05 |
| Contract number | 8253004 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.