# Big Creek Construction, LTD.: TxDOT widen non-freeway contract 100%+ complete, SH 19, Henderson County ($14,745,378, 12 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Big Creek Construction, LTD. |
| Subcontractors | Bahena Construction Co., INC. (7.88%); Cherokee Services (0.12%); Cold Creek Construction, LTD (4.57%); Diamond Elite Barricades, LLC (0.24%); Fortson Contracting, INC. (1.66%); Murray Construction (0.5%); J. H. Oden Contracting Company (1.29%); Striping Technology, L.P. (1.54%); Surface Preparation Technologies, LLC (0.33%); Next Construction Solutions LLC (0%); Flex Supply, LLC (0.03%); 1 Priority Environmental Services, LLC (0.13%) |
| Progress | 103.73% complete, 100.33% of time used |
| Amount | $14,745,378 revised (original $13,887,918) |
| Change orders | $341,699 |
| Paid to date | $14,759,957 |
| Work | Widen Non-Freeway |
| Location | SH 19, 0.3 MI S OF FM1861(VAN ZANDT C/L),S to 0.1 MI N OF SL 7 IN ATHENS (WATSON), Henderson County, Tyler District |
| Let / began | 2024-09-06 / 2025-01-07 |
| Latest estimate | 2026-10-02 |
| Contract number | 9243204 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.