# Big Creek Construction, LTD.: TxDOT interchange (new or reconstructed) contract 80% complete, SH 9, Coryell County ($7,153,291, 7 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Big Creek Construction, LTD. |
| Subcontractors | 4e Tree Worx LLC (0.38%); Austin Traffic Signal Construction Co., LLC (3.88%); Cap River LLC (1.71%); D. I. J. Construction, INC. (0.82%); Environmental Safety Services, INC. (0.99%); Stripe-A-Zone, LLC (0.41%); Woolery Custom Fence Co. (4%) |
| Progress | 79.82% complete, 101.67% of time used |
| Amount | $7,153,291 revised (original $7,187,653) |
| Change orders | $-34,361 |
| Paid to date | $5,709,700 |
| Work | Interchange (New Or Reconstructed) |
| Location | SH 9, OLD GEORGETOWN ROAD to BNSF RAILWAY, Coryell County, Waco District |
| Let / began | 2025-09-04 / 2025-11-17 |
| Latest estimate | 2026-10-05 |
| Contract number | 9253006 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.