# Bk Field Operations LLC: TxDOT maintenance contract 25% complete, Various, Ector County ($2,667,137, 2 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Bk Field Operations LLC |
| Subcontractors | W-Tex Services LLC (61.23%); S & S Bridge Painting, INC. (5.8%) |
| Progress | 25.1% complete, 22.26% of time used |
| Amount | $2,667,137 revised (original $1,656,587) |
| Paid to date | $415,799 |
| Work | Maintenance |
| Location | Various, DISTRICTWIDE to ., Ector County, Odessa District |
| Let / began | 2026-01-07 / 2026-06-01 |
| Latest estimate | 2026-09-30 |
| Contract number | 1263211 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.