# Brice Construction And Design LLC: TxDOT toll road contract 78% complete, SH 99, Harris County ($55,958,674, 25 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Brice Construction And Design LLC |
| Subcontractors | Cpave, INC. (0.88%); Lifthigh Crane & Rigging, LLC (0.22%); Buyers Barricades Houston, LLC (0.08%); Weber-Balke Foundation Company, INC (4.53%); Rexcon Enterprises, LLC (4.3%); Trp Construction Group, LLC (1.55%); Ablemkr, INC. (4.39%); Gmj Paving Company LLC (1.66%); Shaw Drilling, LLC (0.03%); Southwest Road & Safety Contractors, LTD. (0.02%); Highway 1 LLC (1.55%); Jh Contract Field Services, LLC (0.26%); (Inactive)mesa Rod Busters, INC. (0.99%); Sk Concrete Services LLC (0.22%); Texas Environmental Management - San Antonio, INC. (2.37%); Willow City Sign & Rail, INC. (1.18%); Martin Marietta Materials, INC. (0.24%); Ashton Sawing And Drilling LLC (0.57%); Deco Contractors, INC. (7.7%); Mesa Rod Busters INC (0.03%); D&A Welding And Fabrication, LLC (0.03%); Durwood Greene Construction Co. (1.66%); Buyers Barricades, INC. (0.08%); Aggregate Technologies, INC. (0.31%); Emery Sapp & Son's INC. (0.1%) |
| Progress | 77.62% complete, 84.05% of time used |
| Amount | $55,958,674 revised (original $55,689,700) |
| Change orders | $242,971 |
| Paid to date | $43,412,893 |
| Work | Toll Road |
| Location | SH 99, SH 249 to KUYKENDAHL ROAD, Harris County, Houston District |
| Let / began | 2024-02-02 / 2024-06-02 |
| Latest estimate | 2026-09-30 |
| Contract number | 2243202 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.