# Built Right Construction Of Oklahoma, LLC: TxDOT bridge widening or rehabilitation contract 87% complete, US 183, Stephens County ($1,414,784, 6 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Built Right Construction Of Oklahoma, LLC |
| Subcontractors | Fc Traffic Control, INC. (2.16%); Morris County Contractors, L.L.C. (6.63%); S&S Bridge Painting (6.74%); Linear Traffic Markings LLC (1.39%); Clear Restoration, LLC (1.23%); A-Core Concrete Cutting Of Texas, INC. (0.68%) |
| Progress | 86.62% complete, 68.38% of time used |
| Amount | $1,414,784 revised (original $1,341,645) |
| Change orders | $46,794 |
| Paid to date | $1,202,703 |
| Work | Bridge Widening Or Rehabilitation |
| Location | US 183, US 183 AT CLEAR FORK BRAZOS RIVER to ., Stephens County, Brownwood District |
| Let / began | 2025-12-03 / 2026-02-23 |
| Latest estimate | 2026-09-29 |
| Contract number | 12253220 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.