# C. E. Barker, LTD.: TxDOT bridge replacement contract 67% complete, SH 70, Nolan County ($7,106,676, 13 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | C. E. Barker, LTD. |
| Subcontractors | Blacksmith Ventures LLC (4.55%); Penhall Company (0.13%); Dustin Allen, INC. (2.44%); Toro Bravo Construction, LLC (0.98%); Texas Shafts, INC. (11.24%); Jb Pinnacle Group, LLC (4.14%); Texas Clear Cut LLC (0.85%); Wims Environmental Construction, LTD. (0.44%); Lindamood, INC. (2.35%); Ashton Sawing And Drilling LLC (0.1%); Traffic Highway Maintenance, LLC (2.46%); West Texas Rock Resources, LLC (0.17%); Strata Foundation Drilling, LLC (0.65%) |
| Progress | 67.18% complete, 96.33% of time used |
| Amount | $7,106,676 revised (original $7,087,905) |
| Paid to date | $4,761,813 |
| Work | Bridge Replacement |
| Location | SH 70, AT SWEETWATER CREEK to ., Nolan County, Abilene District |
| Let / began | 2024-10-02 / 2025-03-21 |
| Latest estimate | 2026-10-06 |
| Contract number | 10243215 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.