# Castillo Aranda LLC: TxDOT miscellaneous construction contract 93% complete, Various, Galveston County ($762,800, 2 subs)

**Score:** 25/100

| Field | Value |
|---|---|
| Prime contractor | Castillo Aranda LLC |
| Subcontractors | Traffic Systems Construction, INC. (0.67%); Alchelna LLC (0.43%) |
| Progress | 93.36% complete, 120% of time used |
| Amount | $762,800 revised (original $736,599) |
| Paid to date | $687,715 |
| Work | Miscellaneous Construction |
| Location | Various, DICKING MARINE LAB to ., Galveston County, Houston District |
| Let / began | 2026-02-05 / 2026-05-12 |
| Latest estimate | 2026-09-30 |
| Contract number | 2263231 |

## Why this score


Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.