# Cedar Hill Services, LLC: TxDOT maintenance contract 84% complete, US0079, Leon County ($443,604)

**Score:** 35/100

| Field | Value |
|---|---|
| Prime contractor | Cedar Hill Services, LLC |
| Progress | 84.04% complete, 71.62% of time used |
| Amount | $443,604 revised (original $79,658) |
| Change orders | $364,705 |
| Paid to date | $373,459 |
| Work | Maintenance |
| Location | US0079, BUFFALO CITY LIMITS, Leon County, Bryan District |
| Let / began | 2025-12-09 / 2026-02-05 |
| Latest estimate | 2026-09-30 |
| Contract number | 12251702 |

## Why this score
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.