# Ck Newberry, LLC: TxDOT rehabilitation of existing road contract 54% complete, SH 255, Webb County ($26,369,665, 9 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Ck Newberry, LLC |
| Subcontractors | 4e Tree Worx LLC (0.21%); D&G Energy Corporation (0.43%); Acee Construction LLC. (16.89%); Highway Barricades And Services, LLC (1.09%); Murray Construction (0.38%); Penhall Company (0.41%); Soil Tech Advance INC. (0.65%); Texas Environmental Management - San Antonio, INC. (0.35%); Frank Jr Reinforcement LLC (0.85%) |
| Progress | 53.98% complete, 43.01% of time used |
| Amount | $26,369,665 revised (original $26,042,350) |
| Change orders | $327,316 |
| Paid to date | $14,233,960 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 255, FM 1472 INTERSECTION to 0.48 MILES EAST OF FM 3338 INT, Webb County, Laredo District |
| Let / began | 2025-07-02 / 2025-09-22 |
| Latest estimate | 2026-10-05 |
| Contract number | 7253203 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.