# Ck Newberry, LLC: TxDOT seal coat contract 96% complete, SH 100, Cameron County ($6,401,217, 3 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Ck Newberry, LLC |
| Subcontractors | Soil Tech Advance INC. (1.13%); Flasher Equipment Company (2.98%); Highway Barricades And Services, LLC (21.93%) |
| Progress | 96.32% complete, 89.17% of time used |
| Amount | $6,401,217 revised (original $6,373,367) |
| Change orders | $27,850 |
| Paid to date | $6,165,397 |
| Work | Seal Coat |
| Location | SH 100, RETAMA ST. to 1.3 MILES EAST OF SAN ROMAN RD., Cameron County, Pharr District |
| Let / began | 2025-09-05 / 2026-02-23 |
| Latest estimate | 2026-10-02 |
| Contract number | 9253215 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.