# Clark Construction Of Texas, INC.: TxDOT seal coat contract 86% complete, SH 31, Navarro County ($14,920,269, 5 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Clark Construction Of Texas, INC. |
| Subcontractors | D. I. J. Construction, INC. (0%); Dustrol, INC. (0%); Centerline Technologies, LLC (17.24%); Barricades Plus, LLC (3.28%); Peachtree Construction, LTD. (8.64%) |
| Progress | 86.09% complete, 98.34% of time used |
| Amount | $14,920,269 revised (original $14,985,368) |
| Change orders | $-158,199 |
| Paid to date | $12,765,445 |
| Work | Seal Coat |
| Location | SH 31, VARIOUS LOCATIONS to IN THE DALLAS DISTRICT., Navarro County, Dallas District |
| Let / began | 2025-10-09 |
| Latest estimate | 2026-10-02 |
| Contract number | 10253233 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.