# Clark Construction Of Texas, INC.: TxDOT seal coat contract 81% complete, SH 7, Nacogdoches County ($9,466,576, 2 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Clark Construction Of Texas, INC. |
| Subcontractors | Red Sixteen Construction, INC (1.04%); Interstate Barricades & Markings, INC. (10.73%) |
| Progress | 81.49% complete, 66.67% of time used |
| Amount | $9,466,576 revised (original $9,316,843) |
| Change orders | $145,734 |
| Paid to date | $7,711,370 |
| Work | Seal Coat |
| Location | SH 7, FM 2713 to SAN AUGUSTINE C/L, Nacogdoches County, Lufkin District |
| Let / began | 2025-11-06 / 2026-04-08 |
| Latest estimate | 2026-10-05 |
| Contract number | 11253207 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.