# Clark Construction Of Texas, INC.: TxDOT rehabilitation of existing road contract 76% complete, FM 3084, Calhoun County ($4,407,735, 6 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Clark Construction Of Texas, INC. |
| Subcontractors | J & M Contracting, Company (11.75%); Third Coast Services LLC (1.1%); Highway Barricades And Services, LLC (0.54%); Murray Construction (0.55%); (Inactive)hogan Murray, INC. (0%); Interstate Barricades & Markings, INC. (2.4%) |
| Progress | 75.52% complete, 81.33% of time used |
| Amount | $4,407,735 revised (original $4,398,168) |
| Change orders | $1,065 |
| Paid to date | $3,322,170 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 3084, FM 1090 to 0.722 MI N OF SH 35, Calhoun County, Yoakum District |
| Let / began | 2025-07-01 / 2026-02-12 |
| Latest estimate | 2026-10-05 |
| Contract number | 7253043 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.