# Clark Construction Of Texas, INC.: TxDOT seal coat contract 83% complete, FM 1991, Bosque County ($5,528,014, 3 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Clark Construction Of Texas, INC. |
| Subcontractors | Flasher Equipment Company (12.4%); Barricades Plus, LLC (2.55%); Red Sixteen Construction, INC (0%) |
| Progress | 83.14% complete, 84.25% of time used |
| Amount | $5,528,014 revised (original $4,972,194) |
| Change orders | $555,820 |
| Paid to date | $4,595,891 |
| Work | Seal Coat |
| Location | FM 1991, FM 219 to SH 22, Bosque County, Waco District |
| Let / began | 2025-09-05 / 2026-05-13 |
| Latest estimate | 2026-10-05 |
| Contract number | 9253218 |

## Why this score
- Contract over $1M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.