# Copasa INC: TxDOT interchange (new or reconstructed) contract 99% complete, SL 360, Travis County ($81,044,812, 27 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Copasa INC |
| Subcontractors | Texop Construction (0.21%); Silvas Trucking, LLC (0%); Vortex Lining Systems, LLC (1.2%); Perez Construction Co. (0.2%); Dakota Utility Contractors, INC. (0%); Farr Foundation, INC. (6.67%); (Inactive)stripe It Up, LLC (0%); Houston Sawing & Drilling (0.03%); Ygcd, LLC DBA Grind Time Rock Milling (2.32%); Brazos River Contractors LLC (8.02%); Lone Star Paving Company (5.62%); Roadway Specialties, INC. (1.56%); Guerra Underground LLC (15.13%); Hermanos Steel, LLC (0.37%); Texas Traffic And Barricade, LLC (0.07%); Who-B Trucking, INC. (0.36%); Texas Auger Boring LLC (0%); *austin Traffic Signal Construction Co., INC. (2.57%); Jpc Construction, INC. (1.98%); (Inactive)road Maker Contractors (5.65%); Quality Turf Farms, L.C. (0.68%); Dan Guerrero Trucking And Dispatch Services (0%); Trp Construction Group, LLC (1.08%); Statewide Materials Transport, LTD. (0.62%); Melendrez Trucking LLC (0%); Superior Pump Solutions LLC (0%); Straight Line Sawing & Sealing, INC. (0.01%) |
| Progress | 98.6% complete, 99.27% of time used |
| Amount | $81,044,812 revised (original $71,330,416) |
| Change orders | $8,851,145 |
| Paid to date | $79,060,759 |
| Work | Interchange (New Or Reconstructed) |
| Location | SL 360, AT WESTLAKE DRIVE to ., Travis County, Austin District |
| Let / began | 2021-12-01 / 2022-07-05 |
| Latest estimate | 2026-10-05 |
| Contract number | 12213001 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.