# Coppell Construction Co., INC.: TxDOT bridge replacement contract 70% complete, BI 27U, Hale County ($6,997,916, 11 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Coppell Construction Co., INC. |
| Subcontractors | Toro Bravo Construction, LLC (0.17%); F & W Electrical Contractors, INC. (1.15%); M & D Foundation Drilling Industries, INC. (4.41%); Morris County Contractors, L.L.C. (1.39%); Penhall Company (0.19%); S & S Bridge Painting, INC. (1.07%); Total Site, INC. (1.43%); Trp Construction Group, LLC (2.22%); Grider Paving LLC (24.38%); Emery Sapp & Son's INC. (0.05%); Jvh4 Services, LLC (1.43%) |
| Progress | 69.54% complete, 72.76% of time used |
| Amount | $6,997,916 revised (original $6,813,363) |
| Paid to date | $4,738,284 |
| Work | Bridge Replacement |
| Location | BI 27U, FM 3466 to EAST 3RD STREET, Hale County, Lubbock District |
| Let / began | 2025-04-04 / 2025-09-02 |
| Latest estimate | 2026-10-06 |
| Contract number | 4253212 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.