# Coppell Construction Co., INC.: TxDOT bridge replacement contract 100% complete, CR, Hamilton County ($4,204,973, 7 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Coppell Construction Co., INC. |
| Subcontractors | Toro Bravo Construction, LLC (0%); Wolfe Construction Group, Incorporated (0.36%); Dustrol, INC. (0.19%); M & D Foundation Drilling Industries, INC. (7.35%); Highway Traffic Control & Services, LLC (0.25%); Morris County Contractors, L.L.C. (0.57%); Peachtree Construction, LTD. (1.79%) |
| Progress | 99.59% complete, 107.18% of time used |
| Amount | $4,204,973 revised (original $4,196,407) |
| Change orders | $8,567 |
| Paid to date | $4,187,538 |
| Work | Bridge Replacement |
| Location | CR, 0.1 MI S OF LEON RIVER to 0.1 MI N OF LEON RIVER, Hamilton County, Waco District |
| Let / began | 2025-06-04 / 2025-09-05 |
| Latest estimate | 2026-10-05 |
| Contract number | 6253017 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.