# Cornerstone Paving And Construction, L.L.C.: TxDOT overlay contract 87% complete, US 59, Liberty County ($861,829, 6 subs)

**Score:** 25/100

| Field | Value |
|---|---|
| Prime contractor | Cornerstone Paving And Construction, L.L.C. |
| Subcontractors | A1 Erosion Control (0.12%); Stripe Lines, INC. (2.12%); Lonestar Traffic Safety, LLC (0.41%); Southwest Road & Safety Contractors, LTD. (7.62%); Professional Traffic Control LLC (0.95%); Scr Civil Construction, LLC (3.02%) |
| Progress | 87.04% complete, 254.17% of time used |
| Amount | $861,829 revised (original $859,788) |
| Change orders | $2,041 |
| Paid to date | $750,112 |
| Work | Overlay |
| Location | US 59, SL 573(S) to DUDLEY STREET, Liberty County, Beaumont District |
| Let / began | 2026-01-07 / 2026-04-01 |
| Latest estimate | 2026-10-01 |
| Contract number | 1263216 |

## Why this score


Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.