# Cornerstone Paving And Construction, L.L.C.: TxDOT overlay contract 97% complete, SH 105, Liberty County ($2,780,143, 5 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Cornerstone Paving And Construction, L.L.C. |
| Subcontractors | J. H. Oden Contracting Company (0.86%); Batterson, LLP (5.97%); Lonestar Traffic Safety, LLC (0.27%); Texco Services, LLC (6.5%); Professional Traffic Control LLC (0.34%) |
| Progress | 97.4% complete, 104.29% of time used |
| Amount | $2,780,143 revised (original $2,780,143) |
| Paid to date | $2,707,958 |
| Work | Overlay |
| Location | SH 105, US 59, EAST to SH 321, Liberty County, Beaumont District |
| Let / began | 2026-02-05 / 2026-04-17 |
| Latest estimate | 2026-10-01 |
| Contract number | 2263216 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.