# Cornerstone Paving And Construction, L.L.C.: TxDOT miscellaneous construction contract 24% complete, Various, Jefferson County ($2,091,217, 5 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Cornerstone Paving And Construction, L.L.C. |
| Subcontractors | 4e Tree Worx LLC (1.32%); J & M Contracting, Company (4.6%); Southwest Environment Services LLC (0.26%); Stripe Lines, INC. (1.31%); Third Coast Services LLC (3.54%) |
| Progress | 24.49% complete, 10.87% of time used |
| Amount | $2,091,217 revised (original $1,999,855) |
| Change orders | $91,362 |
| Paid to date | $512,219 |
| Work | Miscellaneous Construction |
| Location | Various, DISTRICT WIDE to ., Jefferson County, Beaumont District |
| Let / began | 2025-05-02 / 2025-07-12 |
| Latest estimate | 2026-10-01 |
| Contract number | 5253240 |

## Why this score
- Contract over $1M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.