# Cornerstone Paving And Construction, L.L.C.: TxDOT widen non-freeway contract 95% complete, FM 256, Tyler County ($5,649,262, 6 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Cornerstone Paving And Construction, L.L.C. |
| Subcontractors | 4e Tree Worx LLC (3.44%); Lonestar Traffic Safety, LLC (0.96%); J & M Contracting, Company (13%); Trp Construction Group, LLC (2.81%); Traffic Signs & Lines, LLC (2.45%); J. H. Oden Contracting Company (0.8%) |
| Progress | 94.97% complete, 63.2% of time used |
| Amount | $5,649,262 revised (original $5,598,867) |
| Change orders | $50,395 |
| Paid to date | $5,365,084 |
| Work | Widen Non-Freeway |
| Location | FM 256, US 69, EAST to CLEAR FORK CREEK, Tyler County, Beaumont District |
| Let / began | 2025-07-02 / 2025-09-12 |
| Latest estimate | 2026-10-02 |
| Contract number | 7253216 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.