# D&G Energy Corporation: TxDOT maintenance contract 77% complete, IH0002, Hidalgo County ($1,260,753)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | D&G Energy Corporation |
| Progress | 76.66% complete, 123.78% of time used |
| Amount | $1,260,753 revised (original $1,211,753) |
| Change orders | $45,000 |
| Paid to date | $963,467 |
| Work | Maintenance |
| Location | IH0002, DISTRICT WIDE to VARIOUS ROADWAYS, Hidalgo County, Pharr District |
| Let / began | 2023-06-28 / 2025-01-13 |
| Latest estimate | 2026-10-06 |
| Contract number | 6234626 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.