# D. L. Lennon Incorporated - Contractor: TxDOT rehabilitation of existing road contract 49% complete, FM 1777, Collin County ($6,107,819, 10 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | D. L. Lennon Incorporated - Contractor |
| Subcontractors | Fortson Contracting, INC. (1.16%); Panola Sign & Barricade, INC. (0.33%); Tex Op Construction, LP (1.01%); Rk Hall, LLC (14.5%); Civil Tree Solutions, LLC (0.22%); A R Daniel Construction Services, Incorporated (1.52%); Trp Construction Group, LLC (1.1%); North Texas Traffic Systems Construction (0.23%); Mojica Construction LLC (10.19%); S&L Site Services LLC (1.96%) |
| Progress | 49.12% complete, 61.94% of time used |
| Amount | $6,107,819 revised (original $5,803,762) |
| Change orders | $11,957 |
| Paid to date | $2,856,539 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 1777, CR 677 to SH 66, Collin County, Dallas District |
| Let / began | 2025-12-03 / 2026-04-28 |
| Latest estimate | 2026-10-05 |
| Contract number | 12253203 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.